PROJECT COMPLETED!

126th Street reconstruction - Range Line Road to Keystone Parkway

126th St. was updated to a boulevard between Range Line Road and Keystone Parkway. It was closed with traffic moving west bound only for a duration of the project allowing reconstruction of the south half of the new roadway. The initial phase of work started Monday, August 1, 2016. After phase one was complete vehicles used the new eastbound lane to bring traffic west bound for the remainder of the project while the remaining work was completed. This decision was made as it was felt that westbound traffic into the city core was a bigger priority. Improvements included: 8' multiuse paths on both the north and south sides of the new boulevard, storm water management, erosion control, new curbs and gutters, two lane boulevard, and a new roundabout at Kinzer Ave ,expected to connect to Carmel Drive in the future.