Roundabout Construction and Improvements

Carmel builds roundabouts because of their proven safety record; compatibility with the environment; aesthetics, and ability to make it easier for pedestrians and bicyclists. Roundabouts reduce injury accidents by about 80% and accidents overall by about 40%.

Storm Water and Drainage Improvements

The storm water and drainage projects included in Carmel Link 2.0 are designed to maintain existing storm water infrastructure, construct new infrastructure, address localized drainage issues, and reduce waterway pollution.

Street and Pathway Improvements

Widening and reconstruction of streets creates less congestion, a more responsible impact on the environment, greater aesthetic appeal and increased safety. By adding more bicycle friendly multi-use paths, Carmel encourages citizens to walk, jog, and run.

Projects & Maps

The projects listed below provide general information and will be updated as necessary. Please be advised that construction timelines and construction information are subject to change due to weather or other unforeseen circumstances.

Roundabout Construction and Improvements

4th Street SW and Range Line Road Roundabout

2018

96th Street and Priority Way Roundabout

2018 Spring

96th Street and Keystone Parkway Interchange

2018 - 2019

96th Street and Hazel Dell Parkway Roundabout

2018 Spring

96th Street and Haverstick Road Roundabout

2020

96th Street and Gray Road Roundabout

2019 Summer

96th Street and Delegates Row Roundabout

2019 Summer

106th Street and Towne Road Roundabout

2017 Summer

111th Street and Westfield Blvd Roundabout

2020

116th Street and Towne Road Roundabout

2017 Summer

116th Street and Range Line Road Roundabout

2020

116th Street and Hazel Dell Parkway Roundabout

2017 Summer

116th Street and Guilford Road Roundabout

2021

116th Street and Gray Road Roundabout

2016 Fall

116th Street and College Avenue Roundabout

2021

116th Street and AAA Way and Roundabout

TBD

126th Street and Gray Road Roundabout

2017 Summer

136th Street and Gray Road Roundabout

2017 Summer

AAA Way and Carmel Drive Roundabout

TBD

136th Street and Carey Road Roundabout

2018

Carey Road and Hawthorne Drive Roundabout

2016 Fall

Carmel Drive and City Center Drive Roundabout

2017 Summer

Carmel Drive and Old Meridian Roundabout

July 2018 - September 2018

Carmel Drive and Range Line Road Roundabout

2016 Summer

Gray Road and Main Street Roundabout

2018

Carmel Drive and Guilford Road Roundabout

2017

City Center Drive and Guilford Road Roundabout

2017

Landscaping and streetscape improvements within existing roundabouts

Ongoing

Carmel Drive and Pennsylvania Street Roundabout

2020

City Center Drive and Pennsylvania Street Roundabout

2017

City Center Drive and Range Line Road Roundabout

2017

Executive Drive and Range Line Road Roundabout

2017

111th Street and Spring Mill Road Roundabout

2018

106th Street and Hazel Dell Roundabout

TBD

4th Street SE and Range Line Road Roundabout

2020 Summer

3rd Avenue SW and City Center Drive Roundabout

2018

6th Street SW and Range Line Road Roundabout

2019 Fall

Range Line Road and Medical Drive Roundabout

2019 Summer

Guilford Road and Main Street Roundabout

2019 Fall

Storm Water and Drainage Improvements

3rd Avenue SW storm sewers

2016

Carmel Meadows - Drainage

2017

Carmel View - Drainage

2016

Cedar Pointe - Drainage

2016

Concord Village -Drainage

COMPLETED

Crooked Stick and Crooked Stick West - Drainage

TBD

Foster Estates - Detention

2018

Green Tree Estates - Drainage

2016 Summer - 2018

Harrowgate - Drainage

TBD

Jordan Woodlands - Drainage

2018 - 2019

Monon Swale/Regional Detention

TBD

Old Town - alleys, parking, water quality

2017

Range Line Road - Drainage

2019

Road reconstruction storm sewers

Ongoing

Small structure and culvert lining

2016 Summer - 2018

Small structure replacement program

2016 Summer - 2018

Village of Mount Carmel - Drainage

TBD

Wilson Village - Drainage

2017

Lake Shore Drive East - culvert replacement

2017

106th Street - culvert replacement

2017

Street and Pathway Improvements

96th Street and Keystone Parkway adjacent roadway construction

2018

126th Street reconstruction - Range Line Road to Keystone Parkway

2016 July - 2017 Summer

126th Street reconstruction - Hazel Dell Parkway to River Road

TBD

126th Street path from Keystone Parkway to Hazel Dell Parkway

2019 Summer

Guilford Road - Grand Boulevard to Main Street reconstruction

2019 Summer

Hazel Dell Parkway - Cherry Tree Boulevard to 146th Street widening

2016 Summer

Keystone Way construction to connect to AAA Way

TBD

Monon Boulevard construction and new Midtown Plaza

2018 - 2019

Multi-use path construction

2016 - 2018

Lowes Way connector to Keystone Parkway and Rangeline Road

2018 - 2020

Range Line Road from 136th Street to US 31

2018 - 2019

Southwest Clay - resurfacing and multi-use path construction

2016 - 2018

Spring Mill reconstruction from 111th Street to Main Street

2017 Winter

Duke transmission line buried (4 different phases)

TBD

Range Line Road streetscape with on-street parking

2017 Fall

Gray Road multi-use path construction

2017 Fall

Project Overview Map & Brochure

View the complete overview map and/or brochure guide of all infrastructure improvement program details, showing all Roundabouts, Storm Water/Drainage and Street/Pathway improvements.

View Map PDF

View Brochure PDF

News & FAQs

There are several ways to stay informed of the latest news and information. Sign-up to get email updates, or visit the Projects and Maps section to download PDFs of the infrastructure improvement program overview map and specific project detour maps.

COMING SOON!

The Carmel Link 2.0 mobile app to access real-time traffic reports, delays, detour routes and more.

Press Releases and News

Coming Soon

Press Releases and News

Coming Soon

Mobile App

A mobile app for your Apple and Android devices will be complete this fall. Stay tuned for more details.

Coming Soon

Frequently Asked Questions

Coming Soon

"Making it safer number one and then number two making it easier and quicker for people to get around."

Jim Brainard, Mayor of Carmel

Stay up to date!

x

Subscribe to Carmel Link 2.0 to get construction updates and more straight to your email inbox


  • Follow @carmellink2.0
  • Follow @carmellink2.0
  • Follow carmellink2.0
  • Get updates from carmellink2.0

Contact Us

Joshua A. Kirsh
Engineering Administrator

City of Carmel
One Civic Square
Carmel, IN 46032
Office 317.571.2441

jkirsh@Carmel.IN.gov  |  www.carmel.in.gov
©2016 Carmel Link & City of Carmel. All rights reserved  |  Privacy Policy